Scout Building Addition Progress
July - Permits Received
August - Site preparation started
Sept 10 - Meeting room pad poured
Sept 20 - Porch concrete pad and front curbs poured
Oct 5 - Walls Framed for new meeting room
Oct 12 - New roof sheathed and new exit door installed in main room
Oct 16 - Porch timbering started